Project Start:
Project Finish:
Thu Nov 29, '07
Thu Jan 31, '08


2007 1099-MISC Tasks


ID
Task Name
DurationStartFinishResource Names% Complete
1
BEN Financials data cleanup
20 daysMon Dec 03, '07Fri Dec 28, '07AP[80%],AIT[20%]100%
2
Receive JAT 2007 software and final specifications
1 dayThu Nov 29, '07Thu Nov 29, '07ITS100%
3
Kick off Meeting
1 dayThu Dec 13, '07Thu Dec 13, '07 100%
4
Deliver specifications to AIT
1 dayThu Dec 13, '07Thu Dec 13, '07ITS100%
5
Install 2007 software in test environment
1 dayFri Nov 30, '07Mon Dec 03, '07ITS100%
6
Notify teams of final file specifications and final IRS changes
1 dayThu Dec 13, '07Thu Dec 13, '07ITS,Corp. Tax100%
7
UPHS Acceptance of Timeline
1 dayFri Dec 14, '07Fri Dec 14, '07HUP,Corp. Tax100%
8
AP Acceptance of Timeline
1 dayFri Dec 14, '07Fri Dec 14, '07 100%
9
AIT Acceptance of Timeline
1 dayFri Dec 14, '07Fri Dec 14, '07AIT,ITS,Corp. Tax100%
10
Testing period for UPHS extract
3 daysFri Dec 14, '07Tue Dec 18, '07HUP[20%],ITS100%
11
Testing period for AP extract
3 daysFri Dec 14, '07Tue Dec 18, '07AP[10%],AIT[20%],ITS[70%]100%
12
Formal Notification of Tests
1 dayWed Dec 19, '07Wed Dec 19, '07ITS100%
13
Install production databases
1 dayMon Dec 17, '07Mon Dec 17, '07ITS100%
14
Install 2007 client on AP workstations
3 daysTue Dec 18, '07Thu Dec 20, '07ITS[95%],AP[5%]100%
15
Holiday Break
8 daysFri Dec 21, '07Tue Jan 01, '08 100%
16
Install 2007 client for Payroll
3 daysWed Jan 02, '08Fri Jan 04, '08Corp. Tax[5%],ITS[95%]100%
17
Final Error cleanup
2 daysWed Jan 02, '08Thu Jan 03, '08AP100%
18
E-Mail AIT to move program into production
1 dayThu Jan 03, '08Thu Jan 03, '08AP100%
19
Receive AP extract by close of business
1 dayFri Jan 04, '08Fri Jan 04, '08 100%
20
Receive HUP extract by close of business
1 dayFri Jan 04, '08Fri Jan 04, '08 100%
21
Print 1099 forms from HUP extract
1 dayMon Jan 07, '08Mon Jan 07, '08ITS100%
22
Print 1099 forms from BEN Financials extract (if desired)
2 daysTue Jan 08, '08Wed Jan 09, '08 100%
23
Audit HUP forms
1 dayWed Jan 09, '08Wed Jan 09, '08 100%
24
Audit BEN Financials forms
2 daysThu Jan 10, '08Fri Jan 11, '08AP100%
25
Combine AP / HUP extracts
3 daysMon Jan 14, '08Wed Jan 16, '08ITS,AP100%
26
Martin Luthur King Jr. Holiday
0 daysMon Jan 21, '08Mon Jan 21, '08 100%
27
File for Extension?
1 dayMon Jan 14, '08Mon Jan 14, '08Corp. Tax100%
28
Load combined extract data to production
1 dayThu Jan 17, '08Thu Jan 17, '08ITS100%
29
Manual Entry
3 daysFri Jan 18, '08Wed Jan 23, '08AP100%
30
Remove items under $600.00 from database
1 dayThu Jan 24, '08Thu Jan 24, '08 100%
31
Print 1099 Forms
2 daysFri Jan 25, '08Mon Jan 28, '08ITS100%
32
Audit 1099 Forms
2 daysTue Jan 29, '08Wed Jan 30, '08AP,HUP100%
33
Mail forms
1 dayThu Jan 31, '08Thu Jan 31, '08AP100%


Microsoft Home Page